How to build a house on a limited budget (60 photos). How to build an inexpensive house Suburban frame house for 500 thousand

Who among us does not dream of our own cozy home? Perhaps only the one who already has it. Recently, the Internet is full of offers about building a turnkey house... The demand and price for such offers are undoubtedly increasing. Most do not understand what it is.

What does it mean to "build a turnkey house"? What is the advantage of building a turnkey house?

Despite the demand for turnkey home construction, many customers do not fully understand what this means. This means that the customer will be provided with fully finished and comfortable housing. Such a house will fully meet the wishes of the customer. In this case, the customer will not worry that he did not have time to finish something because of urgent matters, he will simply be provided with the finished work. All that is left for the customer to do is just to celebrate the housewarming. There are definitely many positive aspects in turnkey construction. Firstly, it is a favorable construction price. Secondly, as mentioned earlier, you will not have to disappear from morning to evening at the construction site of the house, but you will only have to move your things to a new house. All internal communications are carried out for the house on a turnkey basis: this is heating, and installation of windows and doors, and hot and cold water supply, and electricity, and sewerage, as well as all finishing work, installation of doors, windows.

The initial stage of turnkey construction.

If you decide to build a turnkey house and find a responsible organization that will do it, then first of all the contractor should offer to develop a working project of the house. It will indicate all the stages of building a house, starting with the preparation of the territory and ending with the exterior decoration of the house. All stages of such construction will certainly be agreed in advance and discussed with the customer. The working design of the house has a very important role. The strength, reliability and comfort of the house depend on the project. A certain period of time is allotted for the creation of a working project. Before starting construction, the contractor and the customer should discuss the construction costs, work schedule and payment. In addition to the working project, a more familiar to us - architectural project is being created. It is required to obtain a building permit from local authorities. It will also be necessary to create a complete project, which will include the design, the structural part and the layout of the communications. It does not matter whether you want to build a house according to an individual or a standard project, in any case, you save yourself from further problems. It is required to remember that regardless of the project, construction should be trusted by certified and experienced specialists.

Building materials for the construction of a turnkey house.

A special place is occupied by the choice of material for external walls. You can choose both gas and foam concrete, brick or wooden beams. Aerated concrete is a relatively new type of building material for external walls. Its popularity is high, because it is light in weight, thanks to this, you can save on the foundation. Aerated concrete has a high level of strength. An aerated concrete house can last over 70 years. The construction of aerated concrete walls is advantageously cheaper than, for example, brick walls. Another advantage of aerated concrete is its environmental friendliness. Beam is also a good material. It will not be difficult to build a house from a wooden beam. After the construction of the box, you need to wait 2 months, since the tree tends to sink. For exterior walls, yellow bricks are often used. It has good thermal performance and is light enough. You can opt for foam blocks. A house from foam blocks is being built quickly and subject to even an inexperienced specialist. Foam blocks are distinguished by their low price, light weight, quick installation, as well as sound insulation. The disadvantages of foam blocks are their fragility and fragility. With the right approach, the house will come out warm, cozy and comfortable. House insulation is of particular importance. If you stopped at facing the house with a bar or brick, then thermal insulation must be done without fail. Unlike timber and bricks, foam blocks have good heat-saving qualities.

The cost of building a turnkey house.

Many people are primarily interested in the construction price. In turnkey construction, the costs of the project, the services of contractors and the cost of materials are summed up. The price can vary due to many factors. An individual project is more expensive than a typical one. If you have a small budget for construction, then it is better to stop at a typical project. The quality of such a house will not be worse than the one that was built according to an individual project. Also, the price will depend on the location of the building, the geological structure, as well as the presence of the basement and the exterior and interior decoration of the house.

Build a house for 500,000 rubles: myth or reality?

Everyone who lived in a rented apartment certainly wants to have his own apartment or house, since not everyone is capable of living in someone else's house and waiting for such a frequent guest as the owner. We have already found out that it is better to build a house on a turnkey basis in order to save our time and money, but is it possible to do this for 500,000 rubles? The Internet "flew" around the blog of a young family who wrote about building a house for 500,000 rubles. There were a lot of commentators. Most insisted that this was impossible, and if it was possible, the house would be damp. Also, commentators assured that such a building would be loved by insects and mold will certainly appear in it. It turned out that it is possible to build a house for 500,000 rubles... The main thing is to calculate everything correctly. To build a house for half a million rubles, you need to have a small plot, about 6 acres, and an experienced contractor.

When choosing a contractor, you need to refer to the following criteria:
1. Does the contractor have experience and work with turnkey orders;
2. Does he have special equipment;
3. Does the contractor provide guarantees;
4. Term of order fulfillment.

The main costs of building a house.

When building a house, there are basic and minor expenses. The main expenses include the purchase of a land plot, if you do not have one, connection to communications, payment for the contractor's work, internal and external finishing.

The costs of building a house are divided like this:
house box-40%,
electricity-6%,
water supply-7%,
finishing works-38%
and heating - 9%.

Turnkey house - buy or build?

Having made the decision to build a turnkey house, you will receive a completely finished and comfortable house that will meet your requirements. What is better, to get a turnkey house ready-made, in which only minor work remains to be done, or to be engaged in its construction? Let's take a look at the positive and negative aspects of each point. Any construction begins with the purchase of land. The positive side of self-erecting a house is the independent choice of land. Choosing a land plot to your taste, you provide yourself with a good location for your future home. Another positive quality is the development of a project on your own, but this type of work takes a lot of time, and without special skills, it will be difficult to do this. Be prepared that it will take a lot of effort and effort to develop a project, purchase building materials. To build a turnkey house, you will need to find a contractor. During construction, you run the risk of running into unscrupulous builders. One of the main advantages, it can be considered, is the ability to perform some work on your own. This will save your budget. Having decided to build a turnkey house, you have the opportunity to pay money to the contractor in stages. Also, the house, which is built on a turnkey basis, fully meets the requirements of the customer. Repair, in the near future, such a house will not require. The ability to independently select building materials can be considered a rather positive point.

Buying a turnkey house.

When buying a turnkey house, you eliminate all the difficulties with its construction, but it is not easy to find a house that will meet your needs. Buying a house, you save yourself from paperwork and this is undoubtedly a plus. When purchasing such a house, you cannot know what materials were used in the construction. You can purchase a home with substandard materials. You can move into a house that has been purchased on a turnkey basis without waiting for the completion of the renovation. Buying a turnkey house, you pay more. If, when building on a turnkey basis, you know in advance the comfort of the location and the nature of future neighbors, then when buying on a turnkey basis, the chances of getting unpleasant neighbors and an unfavorable location are higher. By comparing all the positive and negative aspects of the purchase and turnkey construction, one can draw conclusions. Obviously building a house is much better.

If you have not come to an unambiguous decision to build or buy, then the following recommendations are for you:
1. Before buying a home, think about why it is for sale. Perhaps there are minor flaws in it. It is better to ask the owner about this.
2. After and before buying a land plot, study the soil and check the level of groundwater flow.
3. When choosing building materials for building a house, pay attention to wooden beams. Facing with this material will help keep it warm in winter and cool in summer.
4. When choosing building materials and tools, pay attention to domestically produced goods. Their price is 20-25% lower than imported ones, and the quality is almost the same.

Output.

Turnkey construction of a house is a new phenomenon, but already quite popular and paid for. If you do not have sufficient knowledge in construction, but you want to keep the process of building a house under your careful control, then this construction option will be optimal for you. Often, organizations that carry out such a front of work have good discounts from suppliers of building materials or in building stores, therefore, such construction may be more profitable than building with your own hands. Is it possible to build a house for 500,000 rubles on a turnkey basis? You can build a house for 500,000 rubles, but only in case of austerity... Such a house will turn out to be modest, but in the future you can improve it at will, without any problems. Is it better to buy or build a turnkey house? Even after being fully informed, the choice is not easy. A turnkey house has a design, layout, cladding and other components, such as the customer desires. When choosing a turnkey ready-made house, a positive quality is the speed of implementation. One way or another, you can choose the option that is more optimal for you.

Construction is carried out as soon as funds are available.

Plot. Burian, no fences. There is an iron garage and electric. pillar at the border of the site. The plot itself cost 400 thousand rubles. District of Bashkiria, plot 2 km from the city.

We made a fence, bought pickets for 5 rubles. pcs., crossbars 30 rubles. We painted the garage, paint (drying oil + bomb-aluminum) 300 rubles.

The result is a strip foundation, 120 in height and 40 in width. KAMAZ pgs was bought for 6.t.rub. and about 10 bags of cement. From the moment of purchase, the uch-ka spent about 15 thousand rubles.

We took out a loan of 40 thousand rubles. We bought 10 pallets of aerated concrete blocks, like 36 thousand, they took glue and cement for the remains for mixing.

Masonry work began. So far, 55 thousand rubles have been spent.

The box is ready. Not fully posted (The back wall is off-screen, it will be frame, for the possibility of expanding the house and fine-tuning it to the planned 9.5x9.5).

We bought a uterine bar for 10t.rub.

Frame back wall.

Began to deal with electricity 10 kW. Panel, 3-phase 2 tariff meter, grounding. I assembled it completely myself, the electricians simply attached the vulture to the pole.

Cost 10t.rub. So far, 75 thousand rubles have been spent.

The foundation was waterproofed. Acquaintances fitted the used door at the door. We bought OSB tiles for 7 thousand rubles.

We hired a front-end loader for land work. 2 thousand rubles

Sprinkled on the foundation.

We started to make a temporary roof. We bought 7 rubles worth of bars. and roofing material 2 thousand rubles. Slabs on the crate for 5 thousand rubles. Almost 100 rubles were spent. about.

Wooden windows were added. I'm around 22, baht 53 years old. Workers. I get 10, and my father 14 thousand rubles. I am an electrician and he is a locksmith.

Winter has begun. In late autumn, they made a well, bought 5 rings of 1,200 rubles, half dug up the rest of the drunks themselves. Pipes for communications. We bought 6,000 boards for the ceiling and a concrete mixer for 8.

Spent 120 thousand rubles.

We made a rough ceiling. Then I plan to drywall or stretch.

San. node. Also in April, the water supply and sewerage system were laid. The concrete screed was poured. We bought 2 pallets of bricks, 10 bags of cement, forest sand. We started to make the bathroom.

Spent from the moment of purchase of the site, 130 thousand rubles.

Well spent the other day:

Shower cubicle, according to stock 10.000
Toilet 3700
Washbasin with a pedestal 2000
Two lever mixers 800 each
Sink with legs ala "village" for a temporary kitchen 1500
EPS 7 sheets for 750 rubles
Polypropylene pipes 600 rubles
5 bags of cement RUB 850
Soldering iron rental 200 Total spent from the date of purchase 158,000 rubles.

Civilization is slowly coming. We bought a picrelated Ariston storage water heater for 9000. And the pumping station, according to the action, cost 3800 rubles.

The most important thing.

General form.

Garden. In the garden, cabbage, potatoes, raspberries, currants, grapes, corn, beets, apple trees, thorns, carrots, mint, onions, parsley, cherries and more. And now the extension of the house. It is quite comfortable to live in the built part.

Drew a sketch of the future expansion.

The expansion will be carried out using TIS technology.

We dragged pillows under the foundation. We made a 2 meter formwork and filled in 4 mixes with the remains of cement. Start of the second part of the construction of NICHEBROD INC. CORP. it should be. We are waiting for the salary in July for cement. They also filled it with a septic tank.

TISE and site.

The window was installed the other day, picrelated. They poured 9 meters of the foundation, there are still 9 meters left, but this year, will it work out. Window sill 300 rubles, two foam cylinders 200 each. Roll of foil insulation 50 sq. M. 1300 RUB One of these days I will take Kamaz clay for 2500. The Internet catches us normally, now I downloaded Dexter's first season.

I'll write a shopping list before I forget:

Expanded polystyrene PSB-15 10cm - 51sq.m.
EPS 5cm - 21 tiles 10.500
Substrate under the laminate 50 m 800
5 cans of polyurethane foam 1300
Foam gun 500
China metal door 3000
Electric convector 2kw 2000
Apple and Plum sapling 1200 On the street +7, rain. I put the convector at 18 * during the day and 22 * ​​because two-rate counter. I paid for the e-mail and it turned out to be 1100 rubles for two months.
A plot with a foundation is for sale on our street for 900 tr. So my farm is already calmly pulling for 1.2 mult

As I wanted: Lay the EPS, Folgoizolon, TP pipes, Buy two batteries of 10 sections each, an electric boiler and later a wood-burning boiler.

It turned out: the ceiling is insulated with foil insulation and 10 cm of expanded polystyrene, there is a substrate for the laminate on the floor) 1 convector, you will have to take the second one. I think I’ll spend the winter like this, here people in SIP houses live with convectors. So it goes...

Bought: 12.000r Wood-burning stove Teplodar TOP200
+250 Polyurethane foam
+200 Mailbox Expenses are approximate each month:
Gasoline 1000
Elvo, internet, telephones 1200
Credit (2 months left) 3000
Food and household goods: 5,000 approx.
And 8-10 stays at the construction site every month. Norm.

The stove is roasting, on the street +1. at home 20+ While I burn pallets and wood. waste.

This month I plan to take the slabs and the Makita electric chain saw. I also owe 10,000 on credit card for EPS and PPP.

The main thing is to start. You never know what you can do till you try. We sell ready-made log houses from 1 million (away from the city) with plots. In general, if a commerce company sells such a house, then its fat is at least 500 kopecks. The work is very expensive, so if you do everything yourself, it turns out very affordable. I bought a washing machine for 10.000 and an LCD TV set for 9.000 rubles. EVERYTHING LIKE PEOPLE. In total, from the beginning of construction, about 250,000 rubles were spent. (Including typewriter and TV.) In February I will probably connect IPTV and ADSL Internet. Meanwhile, gas was installed on the street. If it works out, I'll take a loan in the fall and run it. Water is also promised in the spring. The cadastral value of the site is already 850 thousand rubles - a good investment, an increase of 200%. The average electricity bill is 1100 rubles per month, at a price of 2.40 per kW during the day and 1.40 at night. For the whole winter, two gazelles of croaker were bought for firewood at 1,500 rubles each. The temperature in the house is 23 * C, despite the three-meter ceilings. Aerated concrete keeps heat well. So it goes. Here.

You can estimate the future scope of work. Approximate plan until autumn:
Finish the foundation
Build the second half using TISE-2 technology
Make a new large roof
Register house
"Register"
Get tax deduction
Connect gas, make gas heating.
Quit and find a new job.
If you suddenly get rich, make the foundation for the garage.
Stone fence.

Once again, he refused vacation, received compensation for unused vacation pay 12 thousand. Lol. Purchased by:
Kamaz PGS, 5000 rubles
Submersible vibration pump + hose - 1600
12 bags of cement, 3200 rubles
total: 10.000
At the moment, about 260 thousand have been spent.
Today I filled in a meter of the foundation.

Today we finished the main foundation, there are 2 bags of cement left. Tomorrow will begin pouring the faculty under the veranda.

The layout of the extended house needs to accommodate 3 small bedrooms, a staircase entrance and one bathroom.
The "height" shouldn't be too big. 5 meters, for example, is clearly a lot. But at the same time, you need to find a balance so that the usable area is sufficient for the rooms.
It will be a big plus if you don't have to disassemble the old rafters by embedding them in some way.

I chose the cheapest version of the TISE machine. The machine costs 30 thousand, and the walls of TISE will cost me the same.

6 rows are laid out, there are 14. Cement and pgs are slowly coming to an end.

Fence and plot.

Approximately 260 thousand is all invested money, I don’t know how much is left, in principle it doesn’t matter, it’s done for oneself.

Whoever wants to look for plots for themselves is better to look for plots on Avito and in local newspapers, of course, through realtors, they sometimes take in bulk, then cut them in pieces, but I don’t want to feed the system, the main thing is that the land is owned, the type of land IZHS. And whoever has the opportunity, then come and see and find out on the spot. Entrance all year round and good electricity. This is enough.

I have a type of land IZHS, land owned. (No building permit needed, no project needed) So, report. We squeezed a little, bought another 25 bags of cement using a credit card, and 6 cubic meters of sand for 5000. Corners for lintels cost 1000 rubles. Now you can calculate how much approximately (20 blocks left to fill) the walls cost: 2 KAMAZ ASGs were bought, half of the first batch went to the foundation, half of the second batch remained (it will go to the floors).

It turns out that 1 kamaz was used up, (6 cubic meters) net 5000r
55 bags of cement, delivery 13.500r
Masonry mesh 500 rub
Roofing material 300r
Total 20,000 rubles.

Excellent result!

We finished the walls. We've got it. They began to plaster and whitewash.
Polyurethane foam 500 rubles
Lumber on the roof, delivery 18.300 rubles:
Edged boards 18x5x600 23pcs (rafters, mothers)
Bars 10x5x600 7 pcs (uterus)
Edged boards, grade 2 2x10x600 1 cube (crate)
And the money was left only for food ...

Meanwhile, the bedrock is mutating.

On Saturday, they called relatives, dismantled part of the roof and put 3 rafters, we plan to put the rest on next Saturday.
Costs: 500 rubles for self-tapping screws and nails. Also today I ordered a corrugated board, 156 sq. M, 10 meters of skates, 750 self-tapping screws, 140 sq. Meters of membrane for a cosmic sum of 42 thousand rubles for me. Paid by credit card Sberbank. So it goes...

We bought a Hammer screwdriver a 1700 rubles.

Hardware products: staples, nails, screws 500 rubles.

According to an approximate estimate, at the moment, funds have been spent in the amount of 345,000 rubles. A lot of money.

In the meantime, roofing work began.

On the other side, there were not enough boards for the battens. We can buy in addition, possibly with an advance payment. To the city we have 2 km or 20 minutes on foot. 10 minutes by bike.
There is a bus.

We get to work like this: we get up at 6.20.

At 6.50 we go by car to the city (my father and I have the same schedules).

At 7.00 a working cattle truck leaves for the plant, at 7.45 the shift begins.

The shift ends at 16.20, at 16.50 a cattle truck takes it to the city (15 minutes drive) We get into the car and go home, at 17.30 we are already there. If you go straight to work by car, then at 4:50 pm you are already at home, but this is an expensive pleasure.

We don't have a project. Wiring in different ways. The bathroom is hidden, there are already all the sockets on an ongoing basis. The rest of the cables are still along the wall, in the future they will be packed in corrugation and will remain under the drywall. The ventilation will be sewn into the false ceiling.
Bought a cherry seedling "Besseya" 500 rubles.

The roof was almost finished, along the way it turned out that there were not enough skates. Money is tight for now.

Two advertising banners bu 3x6 on gables 1000r Two foam cylinders and a new gun 1000r 3 bags of cement and paint 1000r Total: 3000 Old wooden windows and doors were installed, the paint was tinted by hand. We started pouring the floors. We are slowly paying off the debt on the credit card, there are 24 thousand left.

It took 7 bags of cement for 1800 rubles to fill the floors.
+ paint and a brush on the windows for a total of 2000 rubles.

Today we bought 6 meters of pipe d114 for the chimney. 2350 RUB Cheap galvanized steel burned out.

Tomorrow I will cook and start plastering inside.

I have lived in an apartment since birth, for 22 years, now I cannot be driven back with a stick. Although if I sell a house, it will be enough for me for 3 in a new building. There is freedom, silence. More space to relax, such as buying a motorcycle or motorboat. Garden by hand. In the meantime, we finished the roof - we bought additional skates for 2000 rubles, cement for 600 rubles. We will plaster the back wall. The same is done, a lot of other small work. We covered apple and plum trees in case of severe frosts and so on.

Make up your mind. The last word to adequate people: Thank you who supported, 2 years passed unnoticed.

All in your hands. The idea was to help people who want to deprive the housing issue with their own hands but did not dare. Make up your mind. Don't feed the system with a mortgage.

Short list of building solutions from 200k-poson:

Try to do everything yourself. It's not difficult, since there is the Internet. Margin for work in finished homes up to 300%. Choose the land correctly - Owned, the type of land is desirable IZHS. The road and electricity are key. The rest will follow. Cheap foundation: TISE, MZFL If you do not know at all from what material to build, choose concrete - a classic. Kindergartens, hospitals, houses - basically everything is concrete.

Always keep warm outside (dew point) Read: "Wet Facade" insulation technology.

Do not get carried away with "modern solutions" from "advisors". Foundations for 500 thousand rubles, and other excesses in the theoretical calculation make the cost of building space. Pay attention to old houses.

Download:

Is it possible to build yourself a good, comfortable house for 500 thousand rubles? My regular readers know very well what is possible.

Three years ago, a young scientist aldabulsk I built myself a small (105 square meters) house near Rostov-on-Don. He built the house on his own, in the evenings and on weekends, the construction took three months and cost about half a million rubles:

After the publication of the report on the construction, bloggers-experts issued a lot of expert forecasts: that the house will certainly rot and fall apart, that fungus will start in the walls, that the sewer system will clog with sewage, and the very first snow will bring down the roof ...

Fortunately, wintering has shown that the house is unshakable, and mushrooms, mice and insects categorically do not want to settle within its walls:

Today I can fulfill your request. Anatoly sent me a detailed photo report on the current state of the "house for 500 thousand", which I publish in full. Looking ahead, I note that skeptics will be hurt: their hopes were not justified. Everything is fine with the house and its tenants.

Start of report ---

We welcome everyone who is interested, for any reason, in the fate of our home. Yes, yes, we are alive and well, we have even become one more person over the past time - we have a son. Now he is a little over two years old, and he is a serious man, not a dickhead. In the present, the wife of the guy who built the house is writing to you. We didn't even divorce or kill each other.

So, we have lived in this house for three winters. We are not buried under the ruins of our home, and we do not have bearded lichen and moss, although, removing the cat's hair, I'm not so sure of that. Our foundation did not even bulge or crack, as they experienced in the comments. In the spring, during the continuation of the repair, we raised the linoleum and were fully convinced of this. Our house is not damp, not cold, there are no drafts, however, in the summer heat it warmed up quite strongly, so an air conditioner was purchased almost immediately.

We also admit that the majority of the audience was right about, to put it mildly, the unprepossessing appearance of the house. And although we have got used to it over the past three years - after all, you get used to everything, it was decided this year to impose a brick on the house in order to improve the view. Therefore, with a heavy heart, sacrificing the completion of the interior decoration, we threw all our strength on the outside. For long overdue the need to finish the boxes, well, those things on the edge of the roof, you understand, right?

Anticipating numerous comments on this action, we can assure everyone that this was not done for the purpose of warming, strengthening, or God knows what else, with only one thing - to bring the house into a human form, it is pleasant to look ourselves. This masonry itself is attached to that most beautiful green metal profile, which we did not take off, because there is no sense, but there is a lot of trouble. No brick carries a load, it does not save from dampness and cold, if anything.

The first thing that they gladly removed was the terrible concrete tape around the house, which they themselves had created in a state of insanity. An additional foundation for brickwork, resting on the very controversial slab that holds the whole house, and this site took five cubic meters of concrete, and 32 thousand rubles along with payment for work.

Then they hired workers who erected the wall. They did it for a long time, with numerous smoke breaks and holidays, but in the end they did. The brick itself cost us 54 thousand, our hard workers requested only 10 rubles. for laying one piece - a total of 45 thousand in total for the work. It's pretty cheap.

Then I had to re-do the slopes on the windows, here they also hired the boys. The window sills - or whatever they are called - were installed by the husband himself, in order to save money. I didn't even argue, because you can't stop him if he decided something, as you already understood. It turned out to be quite simple. Especially from the outside observing.

The roof was lengthened, the gaps between the rafters were filled with defective bricks.
The long-awaited moment has come - boxes were made of dark brown laminated waterproof plywood. The surface of the plywood is almost mirrored, so it is hardly noticeable.

From the side of the gables, the brick is covered with ebb tides.

This is the only attractive thing in our fence so far - my husband did it for two nights.

The internal situation has actually changed little, since living together on two salaries and three on one, as they say, are two big differences. Our turn to the kindergarten is only coming up next year, so my so-called vacation has been completely free for a long time.

The bathroom, which is also a toilet, was not photographed, nothing has changed, but mold has not appeared, see for yourself. Ordinary drywall steadfastly withstands the stormy delights of our son while bathing. They just put linoleum and rugs on the floor, it's not cold to walk barefoot. Hanging structure - Ikeev's ceiling dryer, in my opinion, is a great invention that saves space. In general, we have IKEA all over the house, you will see further. Yes, yes, we are rogue, but this is understandable.

And comrades, let's make it clear once and for all - we have a toilet bowl, hot water from an 80-liter water heater and a sewage system that takes it all outside the house, into a hole in the yard. Cold water is supplied to our summer cottages by the Azovvodokanal. By the way, the quality of the water has been absolutely disgusting lately.

Everything is still in the bedroom.

A hallway appeared with a wardrobe, a coat rack and a chest to sit and comfortably put on a child's shoes.

It was decided to turn the so-called cabinet into a nursery in the future. For now, this is a place to store all sorts of nonsense. The door was removed when the son seriously pinched his fingers for the second time. For some reason, it was for this joint that he was inflamed with especially tender feelings.

An extractor hood appeared in the kitchen. The little black thing in the corner on the right is an electric mini-oven, which is quite enough for us. The hob is powered by the same gas cylinder. A juicer sticks out on the cabinet - the most useless unit, as it turned out. By the way, this year we have harvested an absolutely record harvest of everything. We still eat pears and apples from our own garden.

The table was moved to the other side, it is convenient to stare out the window.

The entrance to the hallway was decorated with an arch.

A staircase appeared to the attic floor. We have not yet decided how to decorate the entrance beautifully. Most likely, there will be no living quarters there. But so much space for storing terribly necessary things! Where they were located below, we did not understand.

Outside the large window-door, sooner or later, there will be an open veranda, on which we, most likely, are already gray-haired by that time, will begin to drink tea and jam.

The size of our cat excludes the possibility of purchasing a standard scratching post, so we built it ourselves, from scrap materials (a broken stool and a block).

Usurper cat. The son simply sleeps, does not see the disgrace that is happening.

A terrible monster, such as a stove, acquired upon arrival, was given to his brother in the garage. I personally like the fireplace much more. It warms up just as well, the house heats up very quickly if necessary. Now we are still relatively warm, so we hardly use it. Two electric convectors keep the house at 22 ° C. Who cares, in winter, in frosts, we have an average of 5 thousand for electricity.

This is our second floor and our assorted junk. The ceiling height will be 2.5 meters. What will happen here, we have not yet come up with.

This year, at last, at the cost of incredible efforts, made mainly to persuade neighbors to take part in what was happening, we filled up the road to our house (if anyone remembers how it was here in 2010). While my husband was the chairman of this insane asylum, it was possible to make one and a half kilometers of main roads passable at any time of the year. On this, public funds were ordered to live for a long time. Now everyone who wants to, including us, finishes the rest with their own money.

The technology is simple: a broken brick is leveled with a front loader at the rate of one Kamaz per 50 meters. Further, large crushed stone is crumbled in the same proportion. Somewhere it turned out better, somewhere worse, but now you can drive everywhere. Our street is a curmudgeon, so we saved as much as we could on the road, we even laid some of the bricks by hand.

Only those who have walked a lot in rubber boots on the road can understand our happiness. Even in the spring, we often had to extract the poor fellows from this mess with our "Niva" on various machines.

Also, my neighbors and I had to change old wires for new self-supporting insulated wires at our own expense, now we have no problems with voltage. In general, our main problem is not our roads, but fools, and it is not clear how to deal with this. The board of directors in our partnership changes almost every week, you will not believe, such intrigues are woven here! I would like the forester to come and drive everyone to hell out of the forest, both white and red. My husband has already left the post of chairman for a year and a half, amen. Everything that happens does not have the best effect on the general state of the economy.

More important, I guess. The house is fully decorated as a living space through the BTI and regional architecture, all three of us are registered in it. He has flaws, he is not the prettiest, again, but he is our own. Those who have lived for many years in rented housing know what this is about.

Every year more and more young families with children move to our summer cottage settlement. We are planning with our neighbors to build a playground and a football field together. We have enough land here. That's how we live.

End of report ---

All country cottages are divided into two price groups. Houses up to 500 thousand rubles and elite buildings, costing from half a million rubles. About 70% of all houses on offer belong to the first group. Building such a summer cottage is much easier than buying a one-room apartment in the city.

What is a house up to 500 thousand rubles?

If you are going to buy a cottage for half a million rubles, you need to get rid of all illusions. You need to clearly understand that this is a budget building. It will not be usable throughout the year. But from May to October it will be a wonderful home for all family members.

Moreover, such a building is not a blank and not a semi-finished product. It is quite livable without further cost. Even turnkey finishing will not require excessive financial investments. Such a service will add no more than 25-30% to the total cost, but will save you from a lot of problems.

The layout of such buildings is developed taking into account the small size of the rooms. In terms of the internal layout, such buildings do not differ from their more expensive counterparts. Living in them is also comfortable.

However, the devil is in the little things. Affordable projects of country houses are created from inexpensive timber (often natural drying), they do not spend insulation materials on them, simple finishing materials are used.

Do not think that such a building will be a frank wretched house, into which you will be ashamed to enter. This is quite a solid cottage that is easy and inexpensive to maintain throughout the year.

What is included in the price of a budget cottage?

The cottage includes:

  • Domokomplekt according to the selected project.
  • Pouring the foundation.
  • Establishment of conducted communications inside the house.
  • Exterior and interior decoration.

Frame houses are simple, they can be easily and quickly assembled on any type of terrain. If necessary, they can be easily re-planned or even disassembled before being transported to a new location.

Builders who build such houses assemble home kits without the use of construction equipment. The work takes a few days, about a month is spent on finishing work.